Planning and Control

商科quiz代考 Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Over five quarters, revenue generated by Alpha Enterprises was

Question 1

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Over five quarters, revenue generated by Alpha Enterprises was: 10, 14, 12, 16, 20. Using moving averages for two-quarter time periods, calculate smoothed values for the 2nd, 3rd, 4th, and 5th quarters:

Select one:

  1. a) 12, 13, 14, 18
  2. b) 12, 12, 14, 17
  3. c) 12, 14, 16, 18
  4. d) 12, 14, 16, 20

Question 2 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The parametric estimating technique is typically used in developing definitive estimates.

Select one:

  1. true
  2. false

Question 3

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Gantt charts can be used to track actual vs. planned schedule performance.

Select one:

  1. true
  2. false

Question 4

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Cost estimates:

Select one:

  1. must be accurate to within +/- 5%
  2. distribute project funds according to time lines
  3. are prepared after the budget has been determined
  4. are prepared before the project budget

Question 5 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

‘Earned value’ is a measure of:

Select one:

  1. planned cost
  2. planned schedule
  3. actual cost
  4. work performed

Question 6

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Soft logic means that:

Select one:

  1. task B must follow task A
  2. if task B must follow task A, then task C must also follow task B
  3. task A and task B are carried out concurrently
  4. while task B is depicted as following task A, the dependency relationship is not required

Question 7  商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, the schedule performance index (SPI) is:

Select one:

  1. 1.33
  2. 0.83
  3. 0.80
  4. 1.20

Question 8

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The critical chain approach ties schedules to resource availability.

Select one:

  1. true
  2. false

Question 9

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Project buffers are placed at:

Select one:

  1. the beginning of critical chain activities
  2. the end of critical chain activities
  3. the beginning of project milestones
  4. the end of project milestones

Question 10 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Both PERT/CPM and the critical chain approaches treat resources as bottlenecks.

Select one:

  1. true
  2. false

Question 11

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The Theory of Constraints (TOC) was originally developed:

Select one:

  1. by the Navy
  2. by Du Pont
  3. for the service sector
  4. for manufacturing

Question 12

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, cost variance is:

Select one:

  1. -$100
  2. $100
  3. -$200
  4. $200

Question 13 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Which of the following shows resource allocation over time?

Select one:

  1. resource leveling
  2. resource matrix
  3. S-curve
  4. Resource Gantt chart

Question 14

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Which of the following approaches is likely to call for multitasking?

Select one:

  1. fast tracking
  2. crashing milestone activities
  3. crashing non-critical activities
  4. configuration management

Question 15

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Critical chain rejects the value of the traditional precedence diagram method.

Select one:

  1. true
  2. false

Question 16 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

An advantage of the product-oriented WBS is that it:

Select one:

  1. provides an excellent view of the whole product
  2. focuses on the schedule of the project
  3. focuses on the cost of the project
  4. is logical, and fairly easy to read

Question 17

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The S-curve:

Select one:

  1. provides information about cumulative expenditures at a given point in time
  2. is a resource loading chart
  3. is a scheduling tool
  4. tracks achievement of milestones

Question 18

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

From the Critical Chain perspective, it is generally better to schedule work:

Select one:

  1. Concurrently
  2. Sequentially
  3. in a staggered fashion
  4. so that critical tasks can be crashed early

Question 19

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

A man’s weight represents what kind of measure?

Select one:

  1. interval scale data
  2. ordinal scale data
  3. nominal scale date
  4. precise measure

Question 20 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Typically, feeder buffers are added to resources at:

Select one:

  1. the point where a non-critical chain path joins the critical chain
  2. the beginning of the non-critical chain path
  3. the beginning of the critical chain path
  4. in the middle of non-critical chain path

Question 21

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

According to the Critical Chain perspective, when computing task durations you should:

Select one:

  1. estimate the median duration of the tasks
  2. add buffers task by task
  3. select a duration that has a 90% chance of success
  4. make a best estimate, then multiply it by a fudge factor

Question 22

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Over five quarters, revenue generated by Alpha Enterprises was: 10, 14, 12, 16, 20. Using the exponential smoothing technique, calculate smoothed values for the 2nd, 3rd, 4th, and 5th quarters given that a = 0.5:

Select one:

  1. 12, 13, 14, 18
  2. 12, 12, 14, 17
  3. 12, 14, 16, 18
  4. 12, 14, 16, 20

Question 23

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

A new product faces two pay-off possibilities. It will either make $100 or $120. The probability of making $100 is 0.4, while the probability of making $120 is 0.6. Conduct a Monte Carlo simulation to simulate the new product’s pay-off, using the following random numbers to compute your answer: 83, 28, 82, 36, 91, 9.

Select one:

  1. $110
  2. $112
  3. $114
  4. $115
商科quiz代考
商科quiz代考

Question 24 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

In estimation, estimating a current state of affairs is generally easier than estimating a future state.

Select one:

  1. true
  2. false

Question 25

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, what is project cost and schedule status?

Select one:

  1. under budget, behind schedule
  2. over budget, behind schedule
  3. over budget, ahead of schedule
  4. under budget, ahead of schedule

Question 26

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

A basic premise of time-boxed scheduling is that:

Select one:

  1. perfection is the ultimate goal of scheduling
  2. heavy use of scheduling software ensures project success
  3. ‘You can’t have it all’
  4. it is wrong to scale back on technical features during scheduling, since this reduces the quality of the deliverable

Question 27

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The only time to conduct effective estimation in project management is during pre-project (initiation) phase.

Select one:

  1. true
  2. false

Question 28 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The bottom level of a WBS is called:

Select one:

  1. work package
  2. cost account
  3. code of accounts
  4. chart of accounts

Question 29

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, the cost performance index (CPI) is:

Select one:

  1. 1.33
  2. 1.00
  3. 0.80
  4. 1.25

Question 30

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Using either working time or elapsed time to calculate the time it will take to complete a task produces the same results.

Select one:

  1. true
  2. false

Question 31

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The WBS is useful when:

Select one:

  1. conducting a top-down estimate
  2. conducting a parametric cost estimate
  3. conducting a bottom-up estimate
  4. allocating human resources to tasks

Question 32 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

‘Concrete drying’ is an example of:

Select one:

  1. a working time task
  2. an elapsed time task
  3. a working time and an elapsed time task
  4. hard logic

Question 33

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Good estimation practice requires that estimates be updated when project tracking efforts indicate that critical path tasks cannot be completed as planned.

Select one:

  1. true
  2. false

Question 34

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

If you want to shorten the length of a project, you must:

Select one:

  1. spend more money
  2. shorten the free float
  3. shorten the critical path
  4. cut back on the features you plan to deliver

Question 35

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

An important function of risk assessment groups (RAGs) is to:

Select one:

  1. provide guidance to the organization on how to manage risk
  2. kill projects that are not going to be successful
  3. conduct Monte Carlo simulations on all projects
  4. develop project cost estimates

Question 36 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Multitasking creates harmony among project tasks.

Select one:

  1. true
  2. false

Question 37

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

A problem with time-boxed scheduling is that it requires solid quantitative skills to be able to use it effectively.

Select one:

  1. true
  2. false

Question 38

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The most accurate way to measure earned value (BCWP) is:

Select one:

  1. employ the 50:50 Rule
  2. employ the 0:100 Rule
  3. track milestone performance
  4. use expert judgment of project team members

Question 39

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The internal rate of return is a project selection technique that examines at what point cumulative income more than offsets cumulative investment.

Select one:

  1. true
  2. false

Question 40

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Crashing is used to speed up work and it generally leads to efficient use of resources.

Select one:

  1. true
  2. false

Question 41 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, schedule variance is:

Select one:

  1. -$100
  2. $100
  3. -$200
  4. $200

Question 42

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Definitive estimates are derived from:

Select one:

  1. Top-down estimates
  2. Expert judgment cost estimates
  3. Bottom-up estimates
  4. Order of magnitude estimates

Question 43

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

TOC states that to fix problems encountered by a system or projects:

Select one:

  1. focus on the Gantt chart
  2. fix problems related to all activities on the critical path
  3. fix the bottlenecks
  4. fix problems related to all activities on both critical and no-critical path

Question 44

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Prioritization is the foundation of time-boxed scheduling.

Select one:

  1. true
  2. false

Question 45

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Another name for Gantt chart is precedence diagram.

Select one:

  1. true
  2. false

Question 46 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The most valuable tool for tracking schedule performance is:

Select one:

  1. the PERT/CPM network diagram
  2. milestone charts
  3. S-curves
  4. Gantt charts

Question 47

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

According to the TOC, multitasking often results in:

Select one:

  1. increased quality
  2. increased efficiency
  3. decreased requirements for resources
  4. decreased accountability

Question 48 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

The resource planning tool that enables us to identify who we need to carry out what tasks is called:

Select one:

  1. a resource Gantt chart
  2. a resource ogive
  3. a resource matrix ( also called responsibility chart)
  4. a resource loading chart (also called a resource histogram)

Question 49

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

Which of the following can be described as very crude cost estimates?

Select one:

  1. indirect project cost estimation
  2. preliminary estimates
  3. definitive estimates
  4. conceptual estimates

Question 50 商科quiz代考

Not yet answered

Marked out of 1.00

Not flaggedFlag question

Question text

If an analysis of cost variance for a given month shows we have spent $10, 00 more than we planned, what conclusion can we make?

Select one:

  1. We are experiencing a cost problem
  2. We don’t have enough information to determine project status for the month
  3. We are saving money
  4. We are slipping our schedule